Thailand's
thirst for energy, both for petroleum products and electricity,
returned with a vengeance in 2002, fuelled by economic recovery,
rising transport usage and growing demand in the industrial and
commercial sectors.
Rising oil
prices, especially in the third quarter to October, spurred
by the threat of a US-Iraq war, did not deter the upswing in
domestic oil and gas demand, which was poised to record average
growth of 6% year-on-year, to the equivalent of nearly one million
barrels of oil per day.
Giving an
extra push to the demand for motor fuel was Thais' love affair
with cars, with some 400,000 new vehicles entering Thailand's
congested road system in 2002.
Relatively
stable power tariffs were expected to contribute to an almost
5% rise in national electricity consumption.
A potential
US-Iraq war and the threat of terrorism prompted the government
to come up with a contingency plan to deal with any possible
energy crisis as well as new security measures at petroleum
installations.
On the policy
front, a new Energy Ministry came into existence in 2002 with
the promise of better administration of the country's energy
affairs.
Meanwhile,
the long-awaited verdict on whether the trans Thailand-Malaysia
gas project would finally proceed moved a step closer with Prime
Minister Thaksin Shinawatra showing strong determination to
push the project ahead.
But clouds
of uncertainty continued to shroud the two controversial coal-fired
power plant projects in southern Thailand and the Thaksin administration
has still not clearly spelled out their fate.
Late in
the year, a new major power source for Thailand began to emerge
as Thailand and Burma reached a consensus to embark on the US$5.5-billion
Salween hydro power project.
However,
Thailand's electricity demand in the future is now seen as not
growing at the pace anticipated earlier, prompting a downward
revision in the power demand growth forecast over the next 14
years.
On a more
positive note, the petroleum exploration industry was given
a major boost as the Industry Ministry finally released seven
oil and gas exploration blocks and granted new production licences
to existing concessionaires, after a delay of two years.
Another
positive development, in terms of preventing energy prices from
inflating, was the successful negotiation to ease the terms
of natural gas purchases from the Yetagun field in Burma as
well as supplies from Unocal-operated fields in the Gulf of
Thailand.
PETROLEUM
AND ELECTRICITY DEMAND
SOAR
Thailand's
petroleum demand, excluding consumption from petrochemical requirements,
rose 6.4% in the first nine months of 2002 to 989,500 barrels
of oil equivalent per day (boed) due to the economic rebound.
 |
| The
Ratchaburi power house: More Burmese natural gas has been
used to meet Thailand's appetite for power. |
Growth in
consumption of natural gas outstripped that of refined oil products
due largely to the continued surge in natural gas demand for
power generation.
Power producers,
in turn, have stepped up production to meet rising electricity
demand in the country.
Usage of
natural gas in the period jumped
8.5% to reach 372,500 boed, 90.1%
of which was used for power generation.
Total consumption
of refined oil products
increased 5.1% to 617,000 boed
with demand for every product showing
a rise _ diesel oil was up 5.6%
to 276,400 boed; gasoline up 6.4%
to 124,400 boed; fuel oil up 5.7% to
84,000 boed; aviation fuel up 0.6% to
64,400 boed; LPG up 4.6% to 66,800 boed
and kerosene up 11.4% to 1,100 boed.
Spurring
demand for petrol and diesel
fuel was the sharp increase in new
vehicle sales. Domestic vehicle sales,
excluding motorcycles, in the first
10 months of 2002 soared 39.6% to
325,818 units, consisting of 101,839 cars
(up 25.3% year-on-year) and 223,979
commercial vehicles (up 47.2%), according
to data compiled by Toyota Motor
Thailand Co.
Thailand's
electricity consumption rose
4.5% in the nine-month period to June
2002 to 79,715 gigawatt-hours.
The peak
demand of 16,681 MW took
place at 2 pm on April 4, 2002, breaking
the previous high of 16,126 MW
recorded on April 23 in the previous year,
as temperatures soared.
The Energy
Policy and Planning Office
projected for the full fiscal year ended
in September 2002, the country's overall
electricity demand would be 4.7%
higher than in the previous year.
HIGHER
OIL PRICES

Global oil prices began to climb from
slightly over the US$20-a-barrel range
in the first quarter of this year to the
$24-27 level in the second quarter.
They
then began to move up further by
an average of $1.10 to $2 in the third quarter,
fuelled by stronger demand and
fear of potential military action that
could disrupt oil supplies from the
Middle East.
With
the prospect of a resolution of the
potential US-Iraq conflict emerging in
November, oil prices began to ease to
the range of $22-24.
Pump prices
in Thailand seesawed in
line with world oil prices, touching a
peak in October in Bangkok of 16.49 baht
a litre for 95-octane gasoline and 15.49
baht for 91-octane petrol.
Analysts
agreed that in the near term,
oil prices were likely to remain robust,
however the resolution of the Iraq
conflict would ultimately bring down
oil prices to the average level that
was seen in the past 10-15 years.
CONTINGENCY
PLANS
Lowering
the car speed limit to 80 kph,
curtailing department stores' opening
hours, and rationing fuel in the
worst-case scenario, are among the
contingency energy-saving plans endorsed
by the National Energy Planning Committee
in the event that a US-Iraq
war resulted in an oil shortage.
Officials
affirmed that capping local oil
prices would be the last resort in the
event of an oil crisis resulting from possible
attacks by the United States on
Iraq.
In October,
Thailand bolstered security at
all of its 85 petroleum depots and six
oil refineries after US intelligence officials
warned the government of a possible
threat from terrorist organisations.The extra
security measures came shortly
after the deadly bomb blasts on
the Indonesian island of Bali and followed
recent warnings by several western
countries that major tourist spots
in Thailand could face possible terrorist
attacks.
BETTER
HANDLING
OF ENERGY
AFFAIRS The
management of energy affairs in
Thailand was likely to improve markedly under
the bureaucratic reform put
in place on Oct 1, along with a new cabinet
line-up.
Pongthep
Thepkanchana, 51, who previously
oversaw part of Thailand's energy
affairs, was named Energy Minister with
a brief to improve policy making,
management and oversee the new
ministry.
All relevant
state agencies and enterprises, previously
scattered under the control
of four ministries and the Prime Minister's
Office, are now under the umbrella
of the new ministry.
The
old structure prevented state agencies
from carrying out government policy
in a unified way because they were
supervised by different ministries.
The new
ministry deals with all energy-related
issues including petroleum, electricity,
renewable energy and
conservation.
POWER
DEMAND GROWTH FORECAST
REVISED DOWN
Thailand
has revised down its power demand
growth forecast over the next 14
years due to a downward revision in
economic growth projections and successful
energy conservation.
The
new projections, prepared by the
state electricity load-forecast body, now
estimates Thailand's peak power demand
rising by 1,104 megawatts a year
between October 2002 and September 2006
from a previous projection of
1,285 MW. That will bring the peak demand
in 2006 to 21,648 MW.
The forecast for October 2006 to September
2011 was cut to 1,535 MW a
year from 1,607 MW, bringing the peak
demand in 2011 to 29,321 MW. The
projection for October 2012 to September
2016 was also reduced to 1,806
MW a year from 2,022 MW with peak
demand rising to 38,351 MW in 2016.
The new
power demand projections were
calculated largely in line with the revised
economic growth forecasts which
were projected to rise by 3.5% to
4-5% between 2003 and 2005, due to
the impact of the declining US economy
and as a result of energy-saving
programmes.
The revised
power demand forecast would
cause a delay in the timing of electricity
delivery and purchase from new
plants planned by the Electricity Generating
Authority of Thailand (Egat) and
private power producers both in
Thailand
and neighbouring countries.
THAILAND-MALAYSIA
GAS PIPELINE
PROJECT The
Thaksin Shinawatra administration made
a landmark decision in May
2002, issuing a long-awaited ruling to
proceed with the stalled Thailand-Malaysia
gas pipeline and the related gas
separation plant project, ending years
of confusion, debates and fighting between
opponents and proponents on
whether the two-nation energy projects should
be allowed to go ahead.
The
gas scheme will now proceed but
its planned onshore section passing through
Songkhla province would be slightly
re-routed to avoid the area where
most of the hard-core opponents of
the scheme are living.
A section
of the onshore pipeline of the
gas project will be re-routed to within
a five-kilometre radius of the original
path, where environmental impact
assessment studies have been conducted.
It
was decided that the landing point of
the pipeline, to be laid from the Thailand-Malaysia
Joint Development Area
in the southern Gulf of Thailand, be
moved to Ban Nairat in Tambon Taling
Chan, 4.8 km from its original path
at Ban Kobsak in Tambon Sakom.Both
are in Chana district, Songkhla.
The alternative
route of the 36-inch inland
line is expected to be shorter than
the current route which is 87 km, extending
from the Chana district of Songkhla
in Thailand to Kedah in the northern
Malaysian peninsula. The
re-routing would also mean the
relocation of the two 425-MMcfd gas
separation units to the new pipeline landing
point.
Last
July, Mr Thaksin reassured his Malaysian
counterpart, Dr Mahathir Mohamad,
during the latter's state visit
to Thailand, that the Thai govern ment
would push ahead with the delayed project.
The delayed
pipeline was supposed to
be completed in the third quarter of this
year to transmit 390 MMcfd of gas from
Cakerawala gas field in block A-18
of the JDA to Malaysia.
Opponents
have not given up. In November,
a petition from 1,384 academics calling
for a review of the project was
sent to the prime minister.
They
branded the project as offering more
advantages to Malaysia than Thailand, while
affecting the livelihood of local
residents in Songkhla and failing to
pass environmental impact assessment standards.
But Mr Thaksin
refused to budge, reaffirming
his determination to see the
scheme through.
Meanwhile,
Trans Thai-Malaysia (Thailand)
Ltd, the project sponsor, said
the laying of the gas pipeline was set
to begin early in 2003, with the commencement
of commercial operations expected
by the end of 2004.
COAL-FIRED
PROJECTS
FATE STILL
UNCLEAR The
May 10 government announcement also
dealt vaguely with whether the
two controversial coal-fired projects in
Prachuap Khiri Khan _ the 1,400 MW
facility of Union Power Development Co
(UPDC) and the 700 MW plant
of Gulf Power Generation (GPG) _
could move ahead.
The government
would only say that
it had granted ``permission'' to the
Electricity Generating Authority of Thailand
(Egat), the contractual buyer of
Bor Nok and Hin Krut power, to ``discuss''
and ``resolve problems'' with the
two project sponsors.
The unclear
official statement led to
two conflicting reports from the government.
One suggested that Egat was
told to negotiate with UPDC and GPG
to put off, once again, the supply start-up
dates by a few years and compensation
incurred by the delay.
The
other report said the Thaksin Shinawatra
administration had indeed decided
to scrap the two power plants in
the southern province of Prachuap
Khiri Khan,
but it was reluctant to say so
in public for fear of hurting the investment
atmosphere.
Egat was
asked to exploit contractual loopholes
for terminating the two projects without
paying them penalty compensation, reportedly
11 billion baht.
Two major
sticking points are that the
two sponsors of the projects, worth US$2
billion in total, had failed to complete
project funding arrangements by
April 30 and were unable to promote understanding
among local residents and
environmentalists.
SALWEEN
POWER PUSHED

Thailand and Burma struck a basic accord
to embark on the US$5.5-billion Salween
hydro power project but differences emerged
over where the main power
house should be located.
Rangoon
wanted the main power plant,
with a proposed generating capacity of
3,000 MW, to be built on Burmese
soil, or more specifically in the
Tha Sang district. Bangkok suggested Mae
Sariang district in Mae Hong
Son, the northern Thai town on the
border with Burma, as the location.
The split
of opinion emerged at a recent
discussion in the Burmese capital
between
Burmese and Thai power authorities_
the first formal talks described as
a starting point to an effort to jointly exploit
energy resources from the Salween river
which offers generating potential
of 5,000 MW.
Egat governor
Sitthiporn Rattanopas said
Thailand suggested Thai soil as a location
mainly because it would be easier
to negotiate loans and bring in investors
to the project.
NEW E&P
LICENCES
The Industry
Ministry finally agreed to
award seven oil and gas exploration blocks,
granting new licences to existing concessionaires,
after a two-year delay.
Granting
these permits was among the
last acts of Suriya Jungrungreangkit in
his last two days as Industry Minister before
becoming Transport Minister in
a new cabinet lineup, spurred by the
Thai government's bureaucratic reforms
in October.
Mr Suriya
had deliberately withheld granting
the permits to pressure the firms
involved, especially ChevronTexaco and
Royal Dutch/Shell, to improve
their terms and conditions proposed
in July 2000 as part of the 18th
licence bidding round.
The new
exploration licences would trigger
spending of more than US$32 million
by the concessionaires to explore
the tracts over the first three years,
according to officials.
Five new
production licences were granted
to existing concessionaire groups
led by the Royal Dutch/Shell,
Pacific
Tiger Energy, Harrods and PTT Exploration
& Production Plc (PTTEP).
YETAGUN
TERMS EASED
The Yetagun
consortium, led by UK-based
Premier Oil, has signed an accord
to amend the terms of its Burmese natural
gas sales to Thailand's partially
privatised energy firm PTT Plc
following protracted negotiations.
The deal,
clinched after Burma's cabinet
last October endorsed amendments easing
the terms in the long- term
gas contract, were described as a ``win-win''
situation as they allowed PTT
to pay less for the gas, deferring the
purchase of incremental supplies, while
the developers can increase gas deliveries
to the Thai firm.
The amendments
resulted in PTT paying
about 4.2 billion baht a year less
for Yetagun gas, piped from the Gulf
of Martaban.
UNOCAL
CUTS GAS PRICES
Yielding
to prolonged political pressure, Unocal
Corp agreed to cut the price
of natural gas it sells to PTT Plc. The
reduction, by about five US cents per
1,000 cubic feet of gas or 2% of the prevailing
wellhead prices, would cost the
US energy firm between 12 billion and
13 billion baht in lost revenue for Thai
gas sales over the next 10 years. Unocal
is the largest natural gas producer
in Thailand, delivering about one
billion cubic feet a day from its 13 fields
in the Gulf of Thailand, representing about
a third of Thailand's overall
indigenous gas supplies.